August 10, 2021
Paper Mill Maintenance Services from SVI BREMCO
Paper plants are hotbeds for harsh environments. They produce high levels of dust and heat and are corrosive to structures and equipment. Reducing or eliminating these effects is critical to increasing reliability and minimizing downtime of…
August 5, 2021
Chest Repairs in North Carolina: Project Brief
SVI BREMCO completed an inspection of a pine leveling chest at a paper mill in North Carolina and found hollow-sounding tiles, some poor glaze conditions, and needed to install a new concrete cover.
July 21, 2021
Inspection and Repairs in Kentucky: Project Brief
SVI BREMCO completed an inspection of a power plant in Kentucky and repaired an extensive amount of bricks and installed new Hastelloy steel plates.
July 9, 2021
Common Repairs Performed in Combined Cycle HRSG Plants
Combined cycle power plants are a popular choice in the power industry for electricity production. They offer better efficiency than other options like gas turbines or steams turbines alone. The combined cycle power plant (CCPP) involves two…
June 14, 2021
Why Do Combined Cycle Gas Plant Silencers Fail?
There are multiple sources of noise within combined cycle gas power plants (CCPP) that have to be addressed so they stay under the maximum noise level that a plant is permitted to have. In CCPPs, like simple cycle power plants, you will find…
May 25, 2021
Chest Repairs in South Carolina: Project Brief
SVI BREMCO performed an inspection and repair of chest equipment for a paper mill in SC. SVI BREMCO repaired the hollow-sounding and cracked tiles and installed new tile as needed.
April 28, 2021
Repair vs. Replacement for Critical Valves
Power plants are often faced with deciding whether to repair or replace critical valves when a failure happens, or an inspection indicates imminent failure. There are various factors to consider when making this type of decision.
April 21, 2021
Brick Lining Repairs in Georgia: Project Brief
SVI BREMCO performed an inspection and repair of a tower in a bleach plant located in GA. SVI BREMCO repaired multiple brick windows, cleaned the steel, and applied primer and membrane. SVI BREMCO also Installed new acid brick using vinyl ester…
March 30, 2021
Stock Surge Chest Repairs in North Carolina: Project Brief
SVI BREMCO performed an inspection of secondary stock surge chest equipment and found it mostly in good condition, with some hollow-sound tiles and active leaks that needed repair.
March 19, 2021
Interior Lining Installation in South Carolina: Project Brief
SVI BREMCO performed an interior ling installation for a paper mill in Eastover, SC, and completed extensive repairs of the bricks in the wall, recessed joints, and relined the side walls.
February 26, 2021
Interior Lining Installation in North Carolina: Project Brief
An inspector performed a visual and physical assessment at a plant in Riegelwood, NC, and discovered missing tile, hollow-sounding, and dis-bonded tiles, as well as some cracks in concrete along the exterior wall.
February 22, 2021
U-Drain Repairs in Georgia: Project Brief
A U-Drain inspection at a company in Oglethorpe, GA, found some walls and floors had recessed and needed repairs to properly seal the concrete.